Report Info
Manpower & Safety
Concerns & Next Plan
Site Photos 3 categories · upload up to 10
1 · Initiate0/4
2 · Progress0/4
3 · Clean Up0/2
Building A FL5–270%
FloorStatusDate%
Building B FL5–310%
FloorStatusDate%
Building C FL5–310%
FloorStatusDate%
💾 Data saved to Supabase — accessible from any device instantly
FORIIIA
FORMA CORPORATIONS CO., LTD.
Chapter One Modern Dutch
Daily Progress Report · Interior & Exterior Wall Repair — Parking Building
Contract PS-CH-RBN:P/FORMA/001/2569 · ฿6,500,000 · 180 Working Days
Contract PS-CH-RBN:P/FORMA/001/2569 · ฿6,500,000 · 180 Working Days
— APR 2026
Day — · — · —
FC-DPR-CHR-—-R0
0%
Overall
0%
0 / 77 FL
A0%
Buildings
A:0%
B:0% · C:0%
✓
Safety LTI
0
0 MH Accum
10%
Next Payment
฿1.95M
@ 40% · Jun 2026
All 77 Floors — Building Progress
0
FL Done
0
FL Active
0
On-Site
0
MH Accum
0
LTI
S-Curve — Planned vs Actual
Payment Milestones
✓
งวด1
Sign
Sign
฿650K✅
2
งวด2
40%
40%
฿1.95M🎯
3
งวด3
70%
70%
฿1.95M
4
งวด4
90%
90%
฿1.3M
5
งวด5
100%
100%
฿650K
Received
฿650,000
Outstanding
฿5,850,000
Contract
฿6,500,000
Concerns
Next Plan
Prepared By
Weerapong Wasukaratana
Project Director · License ภย 59410
PMP #2874041 · Forma Corps
PMP #2874041 · Forma Corps
CM / QA
GreenSun (CM/QA)
Construction Manager
Forma Corporations Co., Ltd.
Forma Corporations Co., Ltd.
Acknowledged — Client
Manat Thammatippitayakul
Chapter One Modern Dutch
ATP Management Co., Ltd.
ATP Management Co., Ltd.
FORMA CORPS · "We Sell Certainty." · PS-CH-RBN:P/FORMA/001/2569
FORIIIA
Daily Progress Activity — Site Photos
Chapter One Modern Dutch
Page 2
1
Site Initiate
0 photos
No photos.
2
Site Progress
0 photos
No photos.
3
Site Clean Up
0 photos
No photos.
FORMA CORPS · Photo Record — Controlled DocumentPage 2 of 2
Client Rooms — Separate Contract
Room-by-room tracking · tap to update
PS-CH-ROOM/FORMA/002/2569
0
Rooms
0
Complete
0
In Progress
0
Defect
No rooms added yet.
0
Days Recorded
—
Latest %
0
FL Complete
0
Total LTI
0 recordsAuto-saved on Generate — stored in Supabase
| Date | Day | Weather | Overall% | A% | B% | C% | FL Done | MH Accum | LTI | Saved By |
|---|---|---|---|---|---|---|---|---|---|---|
| Loading records... | ||||||||||
Project Progress Report
Chapter One Modern Dutch
Interior & Exterior Wall Repair · Parking Building · ฿6,500,000 · 180 Working Days
Last updated: —
Building Progress
S-Curve — Planned vs Actual
Latest Site Photos
ℹ️ This is a read-only client view. Data is updated daily by Forma Corporations field team.